To:   HONORABLE MAYOR AND                   From:   Katy Allen

                        CITY COUNCIL

 

   Subject:   ANIMAL CARE CENTER REVISED     Date:   07-23-03

                        CCO NO.  17

 

Council District:  Citywide

 

RECOMMENDATION

 

Approval of Contract Change Order No. 17 with Dennis J. Amoroso Construction for the Animal Care Center - Building and Site Improvements Revised in the amount of $235,000 for a total contract amount of $10,609,560.

CEQA:  Negative Declaration, H01-01-003.

 

 

BACKGROUND

 

On June 4, 2002, Council awarded the Animal Care Center Project and approved a 5 percent contingency for the project.  Currently the project is 72 percent complete and is expected to be completed by November 2003. 

 

Sixteen previous contract change orders have been approved for a total amount of $795,560.  Fifteen changes orders totaling $196,560 were executed to address field conditions and design refinements modifications such as mechanical piping modifications, additional asphalt concrete and lengthening a retaining wall.  In addition, on June 24, 2003 Council approved Change Order No. 12, which provided $599,000 of increased funding for the project to provide for the installation of a steel kennel system.  These previous change orders have also included time extensions totaling 90 days.

.

 

ANALYSIS

 

When this project was awarded, three items were purposefully not included in the contract because of the lack of available funding at the time of the contract award.   These items are:

 

1) a steel kennel system                                                    CCO #12  - $599,000

2) a steel casework (cabinetry) system  Proposed CCO #17  - $225,473

3) a landscaping and irrigation system                Estimate           $400,000

 

These items are necessary for the operation of the facility and to meet the requirements of the site development permit.  During the 2002-2003 Mid-Year Budget Review process, an additional $864,000 was allocated for this project to fund the kennel system and the casework system.  There is sufficient funding to cover the costs of this change order.

 

Proposed Contract Change Order No. 17 will provide for the purchase and installation of the stainless steel casework (cabinetry) in the amount of $225,473.  This is a negotiated lump sum amount which is the best value from three subcontractors bidding this work.  The landscaping and irrigation system will be addressed in the future due to lack of funding.

 

In addition, the requested change order includes installing two channel transmitters to control the two roll-up doors and adding eighteen speakers to the paging system as requested by PRNS staff.  The amount for the two items is $9,527 which brings the total amount for the change order to $235,000.

 

 

PUBLIC OUTREACH

 

Not applicable.

 

 

COORDINATION

 

This proposal has been coordinated with the City Attorney’s Office and the City Manager’s Budget Office.

 

 

COST IMPLICATIONS

 

1.      AMOUNT OF RECOMMENDATION:  $235,000

 

2.      COST OF PROJECT:

Project Delivery

$1,807,000

Land Acquisition

3,321,000

Construction

10,835,378

Proposed Contract Change Order No. 17

235,000

Contingency

        99,440

TOTAL

$16,297,818

 

·        A total of $14,929,000 was expended or encumbered in prior fiscal years for project delivery costs. This project spans multiple fiscal years.

·        To date, sixteen change orders totaling $795,560 have been issued for this project.  The Contingency Reserve of $1,130,000 has been sufficient to cover the costs of these change orders and a balance of $99,440 remains to address future needs.

 

3.      SOURCE OF FUNDING:    001 – General Fund

 

4.      FISCAL IMPACT:  This project is consistent with the Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.  Upon completion, this project will have operating and maintenance impacts to the General Fund, as follows:  PRNS reports that the Humane Society costs the City $186,000 per month for animal control services.  This cost will be eliminated by the new facility.  Operating costs are projected to be $165,000 per month. 

 

 

BUDGET REFERENCE

 

 

Fund

#

 

Appn

#

 

Appn Name

 

RC #

 

Total Appn.

 

Amt. for Contract

 

Budget Page*

 

Last Budget

Action

(Date, Ord. No.)

001

3066

Animal Care and Services Program

013790

$6,157,114*

$214,000

2003-2004 Proposed Operating Budget, Page 679

7-1-03, Ord. No. 26916

001

4813

Animal Shelter Facility

108603

$600,000

21,000

2003-2004 Proposed Capital Budget, Page 799

7-1-03, Ord. No. 26916

 

 

Total

 

$6,757,114

$235,000

 

 

 

*Of the $6,157,114 appropriated in Fund 001 (Appropriation 3066), $864,000 is allocated for this project.  This action was taken during the 2002-2003 Mid-Year Budget Review process to fund cages and a kennel system.  It is recommended that this appropriation fund a portion of the change order costs.

 

 


CEQA

 

Negative Declaration, H01-01-003

 

 

 

 

   KATY ALLEN

   Director, Public Works Department

KWT:PT

8_12_03#7r.doc