Subject: REDMOND AVENUE SANITARY SEWER I&I REDUCTION PROJECT
COUNCIL DISTRICT: 10
Report on bids and
award of contract for the Redmond Avenue Sanitary Sewer I&I Reduction
Project to the low bidder, Insituform Technologies Inc., in the amount of
$685,515, and approval of a contingency in the amount of $69,000. CEQA:
Exempt, PP01-08-137.
An engineering consultant
investigation was undertaken in August 2000
to identify sources of groundwater
infiltration in the sanitary sewer system. This project was one of the areas identified in the
study.
Water currently enters the sanitary
system through pipe cracks and joints in two parallel sanitary sewers located
along Redmond Avenue between Camden Avenue and Cloverhill Drive. The added groundwater increases flows to the
Water Pollution Control Plant (WPCP) and impacts the WPCP’s ability to meet its
Bay discharge flow cap.
This project will install a pipe
liner inside the sanitary sewers to block the infiltration of groundwater. The rehabilitation method selected for this
project does not require excavation except when replacing the sanitary sewer
laterals thus minimizing the construction impact to the neighborhood.
This project is eligible for
reimbursement under the Water Pollution Control Plant’s Infiltration and Inflow
(I&I) Reduction Program. Staff will
pursue reimbursement upon completion of the project construction. The project is scheduled to begin in August with completion in March 2003.
ANALYSIS
Bids were received on March 7, 2002 with the following
results:
|
|
|
Variance Over/(Under) |
|
|
Contractor |
Bid Amount
|
Amount
|
Percent |
|
Engineer’s Estimate |
$2,253,970 |
-- |
-- |
|
Andes Construction,
(Oakland, CA) |
1,373,179 |
($880,791) |
(39)
|
|
Wesco Infrastructure Technologies
(Torrance, CA) |
1,350,370 |
(903,600) |
(40)
|
|
Ford Construction Co. Inc.
(Lodi, CA) |
1,143,770 |
(1,110,200) |
(49) |
|
Gelco Services, Inc.
(Salem, OR) |
808,275 |
(1,445,695) |
(64) |
|
Insituform Technologies, Inc.
(San José, CA) |
685,515 |
(1,568,455) |
(70) |
The low bid submitted
by Insituform Technologies, Inc. is 70 percent below the Engineer’s
Estimate. The Engineer’s Estimate was
based on historic bid prices from the previous year.
The considerable difference
between the Engineer’s Estimate and the low bid is attributed to the pipe liner
and sewage flow diversion costs. In the
past, pipe liners were manufactured and shipped from other states. These
products are now available locally which significantly reduces the shipping and
stock charges. The contractor’s bid to
perform the sewage flow diversion was unexpectedly low. Despite the unexpectedly low bid, the
contractor is obligated to perform the diversion in the manner set forth in
project specification. The above
referenced factors, the competitive market that now exists among rehabilitation
contractors and the downturn in the economy significantly affected the bid
price.
The bid documents have
been reviewed and found to be in order. A ten percent contingency is requested
for this project because the replacement of sanitary sewer laterals and sewer
diversion work will require excavations in challenging ground conditions. The
project budget is sufficient to accommodate the increased contingency.
To solicit contractors, this proposed
project was listed on the City’s Internet Bid Line and advertised in the San Jose Mercury News and San Jose Post Record. Bid packages for all Department of Public
Works construction projects are routinely provided to a standard list of
various contractor organizations, builder’s exchanges, and disadvantaged
business organizations.
This project and memo has
been coordinated with the Departments of Environmental Services, Planning,
Building and Code Enforcement and Transportation, and the Offices of the City
Attorney, Risk Manager and Equality Assurance.
1. COST
OF RECOMMENDATION: $685,515
2.
COST OF PROJECT:
|
Project Development |
$ 10,000 |
|
Construction Contract |
685,515 |
|
Design and Construction Management |
250,000 |
|
Contingency |
69,000 |
Total $1,014,515
3. SOURCE OF FUNDING: 540
– Sanitary Sewer Connection Fee Fund
4. ESTIMATED START DATE OF CONSTRUCTION: August, 2002
5. ESTIMATED COMPLETION DATE OF
CONSTRUCTION: March, 2003
Fund: 540
Appn: 6444
R.C.: 116273
Amount: $2,660,000
Budget
Document: 2001-2002
Appropriation Ordinance Section 4.01, Item 1(h)
Exempt,
PP01-08-137.
KATY ALLEN
Director, Public Works Department